    In the 100-day action plan – the objectives of the Rural Development Department and the details of their achievement are as follows:

    Sec. No. Issue Procedure complete/ incomplete If complete, information regarding it and government decision/photo/etc. records or link to it If incomplete, current status and time limit for completion of the proceedings
    1 Approval of at least 13,00,000 houses under Pradhan Mantri Awas Yojana (Gramin) Phase-2 Complete 13,60,084 houses have been approved under Pradhan Mantri Awas Yojana (Gramin) Phase-2.–>
    2 To disburse a total of Rs. 450 crore as first installment to 3,00,000 approved housing beneficiaries Complete A total of Rs. 2062.06 crore has been disbursed as the first installment to 12,85,553 approved housing beneficiaries under Pradhan Mantri Awas Yojana (Gramin) Phase-2.
    –>
    3 Physically complete at least 1,00,000 houses Complete 1,48,542 houses have been physically completed under Pradhan Mantri Awas Yojana (Rural) Phase-2.–>
    4 Providing land for construction of houses to at least 5,000 landless beneficiaries. Complete Under Pradhan Mantri Awas Yojana (Rural) Phase-2, land has been provided to 23,333 landless beneficiaries.
    –>
    5 To implement a 100-day Maha Awas Abhiyan from January 1, 2025 to April 10, 2025 for effective, fast-paced, quality implementation of rural housing schemes and public participation Complete As per the government decision of the Rural Development Department dated January 01, 2025, a Maha Awas Abhiyan comprising 10 activities has been implemented in the state from January 01, 2025 to April 10, 2025.5- 1.1.2025 GR
    6 Maharashtra State Rural Livelihood Improvement Mission to provide Rs. 2,000 crore bank credit to self-help groups through various banks Complete Maharashtra State Rural Livelihood Improvement Mission to provide Rs. 2606.39 crore bank credit to self-help groups through various banks. –>
    7 Maharashtra State Rural Livelihood Improvement Mission to create 10,00,000 Lakhpati Didis Complete As many as 10,27,918 Lakhpati Didis have been created under the Maharashtra State Rural Livelihood Improvement Mission.–>
    8 Maharashtra State Rural Livelihood Improvement Mission to provide Rs. 300 crore community fund to self-help groups. Complete A community fund of Rs. 463.32 crore has been provided to self-help groups under the Maharashtra State Rural Livelihood Improvement Mission. –>
    9 Setting up 3,00,000 individual/group industries under Maharashtra State Rural Livelihood Improvement Mission Complete 3,15,226 individual/group industries have been set up under Maharashtra State Rural Livelihood Improvement Mission.–>
    10 Complete the training of 1,00,000 people’s representatives in Panchayat Raj Institutions under the restructured Rashtriya Gram Swaraj Abhiyan. Complete A total of 1,20,002 people’s representatives in Panchayat Raj Institutions have been completed under the restructured Rashtriya Gram Swaraj Abhiyan. –>
    11 Creation of Panchayat Study Centers in 79 Gram Panchayats of the state. Complete Panchayat Study Centers have been created in 79 Gram Panchayats of the state. –>
    12 Preparation of Gram Panchayat Development Plans for the year 2025-26 for all 27,945 Gram Panchayats in the state. Complete Gram Panchayat Development Plans have been prepared for all 27,945 Gram Panchayats in the state.–>
    13 Under Pradhan Mantri Gram Sadak Yojana-III, 1500 km. Roads of length 1531.73 km. have been upgraded. Complete Under Pradhan Mantri Gram Sadak Yojana-III, 1531.73 km. Roads of length 1531.73 km. have been upgraded. –>
    14 Under Mukhyamantri Gram Sadak Yojana Phase-2, 2000 km. Complete the upgrading of roads of length in 100 days. Complete Under Mukhyamantri Gram Sadak Yojana Phase-2, the upgrading of roads of length 2600.35 km has been completed in 100 days. 14- 2600.35 MMGSY
    15 The 15th Finance Commission funds have not been received due to the lack of public representatives on the local self-government bodies. The issue regarding elections in local self-government bodies could not be resolved as it is pending in the Hon’ble Supreme Court. Therefore, a letter should be sent to the Central Government to get exemption from this condition. Complete Since 2022, administrators have been working in 26 Zilla Parishads and 289 Panchayat Samiti. Letters have been given to the Ministry of Panchayati Raj and the Ministry of Finance, Government of India, regarding the distribution of funds withheld from rural local self-government bodies due to the active administration.
    1. Signed by the then Hon’ble Minister (Rural Development and Panchayat Raj) Dated 19.7.2023 and Letters have been given to the Hon’ble Minister (Ministry of Panchayati Raj), Government of India on 07.12.2023.
    2. With the signature of the Hon’ble Chief Minister A letter has been sent to the Hon’ble Finance Minister, Government of India on 04.01.2025.
    3. Signed by Hon’ble Principal Secretary (Rural Development and Panchayat Raj)A letter has been given to the Hon’ble Secretary (Ministry of Panchayati Raj), Government of India on 13.01.2025.
    4. In the meeting of the Empowered Committee held in Delhi on 04.03.2025, the Hon’ble Principal Secretary demanded the release of the withheld funds.
    5.With the signature of the Hon’ble Chief Minister A letter has been sent to the Hon’ble Prime Minister on 04.03.2025.
    16 In order to avoid duplication of work with other works in rural areas, including providing basic facilities within the villages as suggested by the people’s representatives, a Single Unified Portal should be developed using the GIS web portal of the Ministry of Panchayat Raj, Gram Manachitra, and an Infra UID should be assigned to each work. Complete As per the letter dated April 4, 2025 of the Rural Development Department, the Single Unified Portal has been made Go Live in all Zilla Parishads from April 01, 2025. 16- 4.4.2025 Single Unified Portal
    17 Under the Road and Bridge Repair and Maintenance Program (3054-2419), 1000 km. Length of work to be completed. Complete Under the Road and Bridge Repair and Maintenance Program (3054-2419), 1200 km. Length of work to be completed on roads has been completed. –>
    18 Under the Punyashlok Ahilyadevi Holkar Rural Yatrasthal Yojana (B Category) to complete 500 works out of a total of 1,587 various development works given administrative approval at 296 pilgrimage sites. Complete Under the Punyashlok Ahilyadevi Holkar Rural Yatrasthal Yojana (B Category) to complete 502 works out of a total of 1,587 various development works given administrative approval at 296 pilgrimage sites have been completed. –>
    19 To provide funds up to Rs. 100 crore for development work for 1348 Tandyas under Sant Sewalal Maharaj Banjara/Laman Tanda Samruddhi Yojana by March, 2025. Complete The funds of Rs. 69.69 crore provided by the Finance Department for development work of Tandyas under Sant Sewalal Maharaj Banjara/Laman Tanda Samruddhi Yojana by the end of March, 2025 have been distributed to the concerned Zilla Parishads. 19- 69.69 Saint Sewalal Maharaj
    20 Construction of Panand roads in rural areas Complete To determine the boundaries of all Shiv Panand farms in the state and construct quality farm roads under the chairmanship of Hon’ble Minister (Revenue) Dated 16.01.2025 and Date 6.2.2025 A meeting was held with the Rural Development and Employment Guarantee Scheme Department on 15th. In this meeting, suggestions were given to study the Nagpur pattern for constructing quality farm roads.
    Accordingly, to get information about the Nagpur pattern being implemented in Nagpur district for construction of farm/land roads, a meeting was held under the chairmanship of Hon’ble Principal Secretary (Rural Development).Dated.14.2.2025 The meeting was held on. In accordance with the said meeting, the report received from the Zilla Parishad, Nagpur has been sent to the Employment Guarantee Scheme Department on 11.3.2025 for further action.
    Also, a meeting was held on 8.4.2025 under the chairmanship of Hon. Minister (Roh.Yo.) and in the presence of Hon. Minister of State (Finance and Planning) regarding the construction of farm/Panand roads.
    Accordingly, further action is expected from the Roh.Yo. Department.
    Total Total number- 20 Total number of completed works- 20 Total number of incomplete works- 0